Deliverables & Milestones

The covid19 pandemic

Due to the 2019 novel coronavirus disease (COVID-19) which diminished the work efficiency of all WPs with local shutdowns, reduced workforce presence, sick leaves (e.g., obligatory 14-day quarantine if even slight symptoms are present) we requested and got a 6 months extension of the TopSpec FET OPEN project (829157). Hence, the milestones and deliverables from autumn 2020 and onward have been extended accordingly.

Updated Gantt chart:
Gantt_approved

Deliverables:

D9.1: Logo and Website launch and public accessibility. – Approved. D9.1

D8.1: IP protection strategy finalized.  – Approved.

D9.2: Data management plan. – Approved. D9.2

D6.1: Modification of the Orbitrap mass spectrometer. – Approved.

D8.2: Exploitation and Dissemination Plan. – Approved. D8.2

D9.3: Technical/scientific review meeting documents – Approved

D3.1: Prototype of the HAB gun installed and tested protocol –
Submitted 31/3 – 2020

D2.1: In situ testing of the optimized CAD MS/MS protocol –
Submitted 30/6 – 2020

D2.2: Protocol of in situ testing of the optimized CAD –
Submitted 28/8 – 2020

D5.1: Prototype pI-Trap-ESI installed and tested– protocol –
Submitted 31/8 – 2020

D2.3: In situ testing optimized ECD, HECD and EID MS/MS –
Submitted 29/6 – 2021

D3.2: Optimized HAB guns installed and tested – protocols –
Submitted 29/6 – 2021

D4.1: Protocol- CED gun prototype installed and tested –
Submitted 29/6 – 2021

Delays:

D1.1:  Two fully equipped Omnitraps & one IMS installed –
Expexted delivery date –  31/10 – 2021

D7.1: Two Prototype FTMS Booster installed and tested-protocol –
Expexted delivery date –  30/9 – 2021

Milestones:

1. Demonstrated effectiveness of product ion isotopic distribution deconvolution. – Achieved.

2. Omnitraps & IMS Electronics design. – Achieved.

3. Installation of Q Exactive instrument for Omnitrap development. – Achieved.

4. Omnitraps & IMS P.O.s sent to suppliers. – Achieved.

5. Omnitraps & IMS Mechanical design.  – Achieved.

6. Data processing algorithms and software for simulated and experimental top-down mass spectra and time-domain data transients – Achieved.

7. Suffic HAB MS/MS demonstrated – Achieved.

Updated by:

Susanna Lundström 2021-07-09