Deliverables & Milestones

Gantt chart:

Deliverables:

D9.1: Logo and Website launch and public accessibility. – Submitted. 28/2 – 2019. D9.1

D8.1: IP protection strategy finalized.  – Submitted 29/3 – 2019.

D9.2: Data management plan. – Submitted 28/6 – 2019. D9.2

D6.1: Modification of the Orbitrap mass spectrometer. – Submitted 20/12 – 2019.

D8.2: Exploitation and Dissemination Plan. – Submitted 20/12 – 2019. D8.2

Milestones:

1. Demonstrated effectiveness of product ion isotopic distribution deconvolution. – Achieved.

2. Omnitraps & IMS Electronics design. – Achieved.

3. Installation of Q Exactive instrument for Omnitrap development. – Achieved.

4. Omnitraps & IMS P.O.s sent to suppliers. Ongoing (finalized Jan/Feb 2020).

5. Omnitraps & IMS Mechanical design.  – Achieved.

Updated by:

Susanna Lundström 2020-09-24